East Coast Main Line Power Supply Upgrade

East Coast Main Line

Network Rail wished to upgrade the power supply on the East Coast Main Line to enable faster, quieter and more environmentally friendly electric rains to run. The upgrade paves the way for the introduction of new trains, such as the Azuma.

Project scope

To facilitate these improvements, they launched the East Coast Main Line Power Supply Upgrade Project, which will be completed in two phases:

  • Phase 1 – covering the route between Wood Green, London to Bawtry near Doncaster
  • Phase 2 – covering the route between Doncaster to Edinburgh

Phase 1

Phase 1 of the project began in 2014 and is planned to be completed by early 2020.

The following upgrades have already been completed:

  • installation of 23 substations along the route
  • laying 600km of new cabling
  • construction of foundations and structures to support overhead line equipment
  • new 400kv connection to the main National Grid

Further upgrades are planned to increase resilience and reliability along the route. These upgrades include additional sub-stations, track based cabinets and feeder stations.

Phase 2

Phase 2 of the project will involve the installation of feeder and substations along the route, capacity upgrades, new 132kv connection at Hambleton junction and upgrades to existing power supply connections.

The second phase of the project is currently in design stages and dates for carrying out the work are still being finalised.

Phase 2 will be delivering upgraded power to the East Coast Mainline railway between Bawtry and Edinburgh and will include:

  • Installing 27 new traction substations
  • Installing 1000 km new cabling including feeder cables and telecoms cabling
  • Construction of supporting foundations and structures for substations and to support overhead line equipment
  • Introduction of 2 New Static Frequency Converter Compounds at 132kV supply connection points

the Rail Electrification (REAL) Alliance

Both phases of the project are being delivered by the Rail Electrification (REAL) Alliance which compromises of:

  • Network Rail
  • Siemens – traction power design, supply, installation and SCADA (Supervisory Control and Data Acquisition)
  • J Murphy and Sons – civil works and structures, cable and cable routes
  • VolkerRail – overhead line equipment works and signalling works
  • TSP Projects – professional consultancy and design support
  • Jacobs – professional consultancy and design support

Facts and figures

  • Client
    Network Rail
  • Value
    N/A
  • Role
    Alliance partner
  • Project categories
    Major projects

Learn more about this project?

Contact Marketing@volkerrail.co.uk »

Related News

More news

East Coast Mainline increases power supply with £216.2M contract award

The East Coast Mainline (ECML) Power Supply Upgrade is to power forward into its second phase, bolstered by a £216.2M...

Powering the next generation of rail travel

An outlined £10 million co-investment agreement has been signed by the University of Leeds and the companies involved...

REAL biodiversity enhancement

The REAL Alliance, currently undertaking the East Coast Main Line (ECML) Power Supply Upgrade project, has made a...

+