icon-arrow-right icon-play icon-close
HomeNewsMilestone reached on construction of Bamford loop for Hope Valley Railway Upgrade

Milestone reached on construction of Bamford loop for Hope Valley Railway Upgrade

Recent

Progress is continuing on the Hope Valley Railway Upgrade, as the VolkerRailStory joint venture continues to undertake essential improvements to the line between Manchester and Sheffield.

Bamford 2.jpg

Recent line closures have seen major work completed, with key milestones achieved by the project team, including a bridge extension in Bamford to facilitate the new passing loop between Bamford and Hathersage stations.

During a 28 hour closure of the railway line in November, the 11m span bridge deck was installed by VolkerRail’s Kirow team, overcoming the challenges that arose by working near an oil pipeline.

Two Kirow 1200 cranes installed the bridge, weighing 58 tonnes, and a total of 172m3 of concrete was used for the base structure.

Recent months have also seen improvements undertaken elsewhere along the route. The lift shafts for the new, accessible footbridge, have been constructed at Dore & Totley station, and track upgrade work has been carried out along the line near Stockport.

Graham Whitehead, senior sponsor at Network Rail, said: “The Hope Valley project team has been working hard to deliver a huge amount of work in recent weeks to ensure that key elements of construction are completed on time.

“Work is progressing well, with the scheme well on its way to delivering benefits and improved reliability for passengers travelling via train between Manchester and Sheffield.”

Martin Smith, board member from the VolkerRailStory joint venture, said: “It is testament to the expertise and dedication of the teams at Hope Valley that the huge amount of work to maintain the programme has been delivered, whilst facing the challenges of extreme weather. Thank you and well done.”

Over the next six months, the VolkerRailStory joint venture will complete the final stages of work, including installing the remaining footbridge in Dore & Totley, track replacement work in Grindleford and signalling improvements along the line.

The Hope Valley Railway Upgrade involves the construction of new infrastructure and track, and signalling improvements to remove bottlenecks along the line, and allow passenger trains to pass slower freight trains along the route.

Once complete, the scheme will improve reliability and journey times of trains travelling between Manchester and Sheffield.

News

More news

Significant earthworks completed on Hope Valley Railway Upgrade

Major progress is being made on the Hope Valley Railway Upgrade, with the majority of earthworks, which set the foundations...

Track-laying between Bicester and Bletchley nears completion

Track laying of the first connection stage of East West Rail (EWR) between Bicester and Bletchley is now 99% complete, after...

Final track installed for Bamford passing loop to remove historic bottlenecks along...

The final pieces of track have been installed to help relieve a long-standing bottleneck on the Hope Valley railway line,...

+